Green Valley Substation Rebuild

It took a team effort to rebuild the Green Valley Substation

Built in 1973, the Green Valley Substation (Green Valley Sub) needed an upgrade. So, in May 2022, Trico hired the firm TOR Engineering to come up with a plan for the rebuilding of the Green Valley Sub.

“Given the age of the substation, its limitations and the fact that we just finished rebuilding the 69 kV transmission line from the Bicknell Substation to Green Valley, it made sense to rebuild it,” said Roger Patnode, the Project Lead.

A decision was made to rebuild the whole substation.

“Starting with the Three Points Substation, we came up with a standard way of designing the 25 kV side of the substations,” Patnode said. “We’re using the same design for the new Adonis Substation and when we rebuild the Marana Substation.”

Like the SaddleBrooke Substation, Trico controls the 69 kV transmission line into the Green Valley Sub. At our other substations, Arizona Electric Power Cooperative Association (AEPCO) handles the 69 kV transmission line.

“At Green Valley, we designed the 69 kV side with a ring bus,” he said. “It provides us with more flexibility for expansion in the future.”

A ring bus configuration is an extension of the sectionalized bus arrangement and is accomplished by interconnecting the two open ends of the buses through another sectionalizing breaker. This results in a closed loop or ring with each bus section protected by a circuit breaker.

The rebuild was done in two phases. In July 2022, Trico started rebuilding the 25 kV side of the substation, south of the existing substation. The Green Valley Sub remained energized during this phase. In November 2022, the old substation was deenergized and demolished and the new 69 kV side was built during this phase.

“We picked up the Green Valley Sub circuits from Bicknell,” Patnode said. “We were able do it because loads are low in the winter.”

The Green Valley Sub was reenergized by May 2, 2023, just in time for summer. Patnode said a lot of work from different departments went into the rebuilding of the Green Valley Sub.

“It was a joint effort,” he said. “It starts with engineering. Then procurement – acquiring the needed equipment and materials. Operations and the Substation and Meter Technicians were also involved in the project. Kudos to everybody who worked on the project.”

Patnode said the two new 20 MVA transformers should last at least 30 years.

“The original transformer was 50 years old and still working when it was retired,” he said.

Construction continues at Chirreon Solar & Battery Facility

Trico employees and contractors from SOLV Energy continue working at the Chirreon Solar and Battery Storage Facility, located on Edwin Road west of North Oracle Road within Pinal County.

Chirreon will have over 40,000 photovoltaic solar panels, and the 15-megawatt battery storage system will be capable of discharging 30 MWh of energy. The facility will help Trico delay the cost of transmission and distribution upgrades and manage load in a more efficient and cost-effective manner.

Chirreon is projected to be in service by summer 2022. Once operational the Chirreon facility will produce more than 30,000 megawatt-hours of energy each year, or enough to power about 3,000 average residential homes in the Trico service territory.

Notice of hearing for Saguaro to Marana Transmission Line Project

A public hearing will be held before the Arizona Power Plant and Transmission Line Siting Committee (“Committee”) regarding the Application of Arizona Electric Power Cooperative, Inc. (“AEPCO”) for a Certificate of Environmental Compatibility to authorize construction of authorizing construction of a 115 kilovolt (“kV”) transmission line called the Saguaro to Marana 115/138 kV line (“Saguaro to Marana” or “the Project”).

The Project consists of two separate transmission line configurations. One portion of the Project is a double-circuit 115/138 kV transmission line to be jointly owned by AEPCO and Tucson Electric Power Company (“TEP”) (the 115 kV circuit will be owned and operated by AEPCO, and the 138 kV circuit will be owned and operated by TEP); the other portion of the Project is a single-circuit transmission line owned and operated by AEPCO alone. The transmission line originates at Trico Electric Cooperative’s planned Adonis Substation.

The hearing will be held at the Northwest Fire Department Training Facility, located at 5125 West Camino de Fuego, Tucson. Arizona 85743. The hearing will begin on Monday, June 6, 2022, at 1 :00 p.m., and will continue on Tuesday, June 7, 2022, at 9:00 a.m. and will continue as necessary on Wednesday, June 8, 2022, Thursday, June 9, 2022, and Friday, June 10, 2022, commencing at 9:00 a.m. on each day through the completion of the hearing. If any revisions to the hearing schedule are required, they will be noticed on the Project website at: www.azgtsaguaromarana.com , and on the Arizona Corporation Commission (“Commission”) website at: https://www.azcc.gov/arizona-power-plant/meeting-schedule.

Click here to read the full notice.